Variance — approvedSE-03-05-029

Orange CountyBoard of Zoning Adjustment

Heard May 1, 2003

Vote
Not recorded
Jurisdiction
Orange County
Orange County
Meeting body
Board of Zoning Adjustment
Case number
SE-03-05-029

Summary of the decision

SE-03-05-029 — Progress Energy Florida, Inc.

Request: Special Exception in R-1 (single family-5,000 sq. ft. lots) zone for public utility (electrical substation).

Decision: Approved

Hearing: The Staff Report and Recommendation is located on Pages _____ Two neighboring property owners to the west in the Sundance at the Econ Subdivision addressed the BZA on this application. One resident opposed the request based on aesthetics, inconvenience due to construction activity, and health issues (electromagnetic frequency emissions). The Progress Energy representative explained the emissions from the proposed substation will be less than that carried in the transmission lines that have existed in the area for several decades. The other property owner spoke in favor with the one request that the applicant install a brick wall finish that will aesthetically compliment Sundance's entry wall.

Affected parcels

Links open the Orange County Property Appraiser record for each parcel.

Provenance

Extracted from the official meeting record on Jul 24, 2026. Extraction confidence: 95%. Always confirm against the adopted minutes before relying on this decision in a filing.