Summary of the decision
SE-06-02-002 — Orlando Utilities Commission
Request: CONSTRUCT ELECTRICAL SUBSTATION
Decision: Approved
Hearing: The applicant gave the BZA a summary of the need for current electrical service, particularly that for backup during storm and hurricane outages, and of future service needs in this area, which includes Innovation Way.
There was no opposition present at the public hearing. The applicant agreed with the conditions of approval.
Affected parcels
Links open the Orange County Property Appraiser record for each parcel.
Provenance
Extracted from the official meeting record on Jul 24, 2026. Extraction confidence: 95%. Always confirm against the adopted minutes before relying on this decision in a filing.