Orange County — Board of Zoning Adjustment
Heard July 5, 2001
- Vote
- Not recorded
- Jurisdiction
- Orange CountyOrange County
- Meeting body
- Board of Zoning Adjustment
- Case number
- 7/5/2001 #9
Summary of the decision
7/5/2001 #9 — UNIVERSITY PRESBYTERIAN CHURCH
Request: (NW of NW 16-22-31 Tract Size: 25.4 acres
Decision: Partial Approval
Hearing: The Staff Report and Recommendation is located on Pages 112, 113 and 114.
This case was first heard by the BZA on May 3, 2001. Since then, the applicant, staff, the district BZA appointee and the surrounding neighbors met to resolve outstanding issues. It was agreed the applicant would proceed with only Phase 1 of the project and defer the future Phases for a later date.
Staff presented the conditions of approval as agreed by all parties. The applicant asked for minor changes to some of the conditions. Two (2) residents to the north asked for additional changes to the conditions.
The BZA agreed with the suggested changes.
Affected parcels
Links open the Orange County Property Appraiser record for each parcel.
Extracted from the official meeting record on Jul 24, 2026. Extraction confidence: 95%. Always confirm against the adopted minutes before relying on this decision in a filing.